How is it possible to apply 2 different overhead rates for 2 different finished goods?

Go down

How is it possible to apply 2 different overhead rates for 2 different finished goods?

Post  michael_fico on Fri Mar 23, 2012 6:56 pm


It is possible through overhead groups. You configure 2 overhead keys.
Define rates for each of this overhead key. These two overhead keys is
then assigned to the two overhead groups. These overhead groups are
attached in the costing view of the finished goods material master.

michael_fico

Posts : 163
Join date : 2012-03-23

Back to top Go down